How to Run a 12-Week ERP Implementation
Most ERP projects take 6 to 18 months. We’ve taken them live in 12 weeks, and had a Czech ERP ready in 16. The client then halted that go-live.
The licence and the partner quote are the easy part of an ERP project budget. What overruns is your own people’s time, the data, the testing and the months after go-live. Put them in the 2027 budget as named lines.
It is October, the 2027 budget is due in a few weeks, and the ERP project finally has a line in it. You have a quote from the implementation partner and a licence proposal from the vendor. Add them up, add something for contingency, and the number goes to the board. A year later, the project is over budget, and almost none of the overrun is in the partner’s invoice.
An ERP project budget usually goes wrong in the costs nobody sends you a quote for. This article lists them, so you can put them in now as named lines rather than discover them in the second half of 2027.
The vendor quote covers licences or subscriptions. The partner quote covers configuration, some development, a defined number of training sessions and go-live support for a set period, all based on assumptions about how ready you are. Read those assumptions carefully. They usually say that your team will be available, your data will be delivered clean, and decisions will be taken on time. Each of those is a cost on your side of the table.
The key users from finance, sales, purchasing and the warehouse will spend a large share of their week on the project for months: in design workshops, testing, data cleanup and training their colleagues. That time is real even if no invoice arrives for it. Estimate it per person and per phase, and agree it with their managers before the project starts, not when the testing begins and month-end close is the same week.
If your best accounts payable clerk spends half their week in testing, someone has to process the invoices. Either you budget for temporary help or overtime, or the day job suffers and the project slips. Backfill is the line most often missing, and its absence is the most common reason key users quietly stop showing up for project work.
Partners migrate data; they do not decide which of your customer records is true. Cleaning customers, suppliers, items and prices is business work, and for a company with years of history it is weeks of it. Budget for the people who will do it and for at least two full test migrations.
User acceptance testing needs people who know the processes, real scenarios written down in advance, and time to retest after fixes. If the testing budget is “the key users will do it”, see line 1.
Every system that talks to the ERP (webshop, CRM, warehouse system, bank, e-invoicing provider, payroll) needs an interface built or rebuilt, and every report the business relies on needs to exist in the new system. These are often outside the partner’s scope or covered by a single estimate. Make a list of each one and give each a line.
The partner’s go-live support usually covers a few weeks. Stabilising a new ERP takes longer than that: the first month-end close, the first quarter-end, the first inventory count and, above all, the first year-end close all happen on the new system for the first time. Budget for support through those moments, whether from the partner, an application manager or an embedded consultant.
Someone in your organisation has to own the project day to day: chase decisions, protect the scope, manage the partner and report to the board. If that is a director doing it on top of their job, the project gets the hours left over. If you do not have that person, budget for one, internal or external, for the whole duration including hypercare.
A contingency line that gets spent on something else in the second quarter is not a contingency. Hold it centrally, decide in advance who can release it and for what, and report against it monthly.
An ERP project budget is also a cash-flow plan. Most of the internal cost lands in the build and test months, and the support cost lands after go-live, often in the next financial year. Two timing questions are worth settling in the budget round:
Before the number goes to the board, check that each of these has its own line, an owner and a month in which it is spent:
The partner quote is the part of an ERP project budget you can see. The overruns come from the rest: your own people’s time, the work behind clean data and proper testing, and the months after go-live that nobody quoted. Put them in the 2027 budget as named lines now. A larger number approved in November is a much easier conversation than an overrun explained in September.
How to Run a 12-Week ERP Implementation
Should You Go Live With Your New ERP on January 1?
The Hidden Costs of Failing Post-Go-Live Support
Carve-Out ERP Separation: Getting Off the Seller’s Systems Before the TSA Runs Out
Thomson Reuters: How to budget for an ERP implementation project
KEEP READING
Most ERP projects take 6 to 18 months. We’ve taken them live in 12 weeks, and had a Czech ERP ready in 16. The client then halted that go-live.
A January 1 ERP go-live gives you a clean fiscal year and costs you a holiday cutover and a finance team that is already closing. Here is how to decide, while the date can still move.
Post-go-live support costs what it costs whether you budgeted for it or not. Seven places the money actually goes when support is under-resourced, and what a properly funded arrangement looks like instead.