ERP selection goes wrong when demos come first. Define your processes, requirements and KPIs, then make vendors show your process with your data.
Most ERP selections start with demos. A few vendors are invited, each one shows a clean order flow on clean demo data, and the team leaves impressed. A few weeks later, the choice is made on screens, features and a feeling.
Then the implementation starts, and the real questions arrive. How do we handle returns? What about customers with three delivery addresses? Who approves a credit note? None of it was in the demo, because nobody asked.
A good ERP selection works the other way around. First you decide how the business should run. Then you check which software supports that best.
A demo is a sales presentation. It is built to show the strongest parts of the product, on data that has no exceptions. That is fine, but it means a demo tells you very little about your own business.
Selections that start with demos usually run into three problems:
Start with the main flows, from trigger to result. For most SMEs that means:
Talk to the people who do the work, not only to their managers. Write down the steps, the handovers, the systems and spreadsheets used, and where it goes wrong. Keep it simple: a page per flow is enough.
This is the step most selections skip. A new ERP is the moment to remove steps that only exist because the old system could not do better. If you copy today’s process into new software, you pay for a new system and keep the old problems.
For each flow, decide what should change and why. Link it to a few business KPIs you want to improve, for example order lead time, orders delivered complete, or time spent on manual corrections. Those KPIs will guide the selection, and later the project.
Now write the requirements, based on the future process:
Keep the list short enough that you can actually test it. Fifty sharp requirements are worth more than five hundred generic ones.
Instead of a standard demo, give each vendor a script: two or three of your real flows, including the exceptions, and a sample of your own data. Ask them to show how the system handles it, and to say openly where they would need customisation.
Score each vendor on the same script, with the people who do the work in the room. A system that needs few changes for your key flows will usually be cheaper and easier to keep up to date.
The software is only part of the choice. Also look at:
An ERP selection needs one owner on the company side, with the authority to decide. It also helps to have someone independent at the table: a person who knows ERP projects, has no stake in which vendor wins, and keeps asking how each option serves the business KPIs.
Ben Van Aken has led ERP selections and migrations, including a selection that resulted in Microsoft Dynamics 365 Business Central. He approaches them as a business generalist: process and KPIs first, software second.
The best ERP selection is not the one with the most impressive demo. It is the one where the company knew what it wanted before the vendors arrived. Define the process first, and the software choice gets much easier.
KEEP READING
Every business has processes. Most have never mapped them. Here’s how to start and why it matters.
Most SMEs that start an ERP or CRM project ask whether to sign with an implementation partner or bring in an independent consultant. The two roles do different jobs, and the projects that struggle usually expected one of them to do both.
The licence and the partner quote are the easy part of an ERP project budget. What overruns is your own people’s time, the data, the testing and the months after go-live. Put them in the 2027 budget as named lines.
Talk to Ben Van Aken, freelance ERP/CRM project lead, on-site, hybrid or remote. Details at swiftly-business-consulting.com.
Currently accepting new engagements, starting now and into 2027.
Comments
Loading comments…